TIMELINE AND ILLUSTRATIONS

In February 2006, the Whittier College Board of Trustees approved the renovation of the current Campus Center building. Our architect completed the schematic design process and we moved into the design development process. After reviewing the second set of design development drawings, we went through the cost estimating phase. A preliminary design development package was submitted to The City of Whittier for approval to proceed with the project. The college met with the City’s Design Review Board on August 24th and it was wonderfully successful and they approved our project. The next step will be the session with the Planning Commission on September 18th.

Once we get the permit and start construction, we have a 12 month construction period. We expect to have a grand opening in the fall of 2007.